• About
  • Advertise
  • Newsroom
  • Contact Us
Monday, March 20, 2023
No Result
View All Result
NEWS ALERTS
GantNews.com
62 °f
Clearfield
  • Home
  • Top Stories
  • News
    • Top Stories
    • A & E
    • Business News
    • Crime
    • Local News
    • Explore Jefferson
    • Features
    • Health News
      • Health & Wellness
    • Sports
      • Local Sports
  • Obituaries
  • Opinions
  • Classifieds
    • Real Estate
  • Health & Wellness
  • Home
  • Top Stories
  • News
    • Top Stories
    • A & E
    • Business News
    • Crime
    • Local News
    • Explore Jefferson
    • Features
    • Health News
      • Health & Wellness
    • Sports
      • Local Sports
  • Obituaries
  • Opinions
  • Classifieds
    • Real Estate
  • Health & Wellness
No Result
View All Result
GantNews.com
No Result
View All Result
ADVERTISEMENT
Home News Local News

CMA Waiting for Greenlight for Alarm System Project

by Kimberly Finnigan
Thursday, December 19, 2019
in Local News, Top Stories
0
0
3
SHARES
0
VIEWS
Share on FacebookShare on Twitter

CLEARFIELD – The Clearfield Municipal Authority is waiting for the green light for an alarm system at Montgomery Dam.

At Tuesday’s meeting, the authority heard from Engineer Jim Balliet of Gwin, Dobson and Foreman, regarding an alarm system at the dam.

Balliet said the authority submitted a comprehensive monitoring plan to the Department of Environmental Protection on Aug. 19, along with an alternative schedule for compliance with the alarm shutdown requirements.

Balliet said the authority has proposed to DEP to submit the public water supply permit by the end of the year and asked for a one-year timeframe, after the permits have been issued, to complete the project.  He said the authority is now waiting for a response from DEP.

Balliet said in order to comply with the new DEP regulations, the water treatment plants must have an alarm system, which will activate a shutdown system, if problems occur at the plant when there is no staff present.

Balliet said system at the Montgomery Dam is 30 years old and can’t comply with the new regulations. He said he and CMA Manager John Williams met with the plant operators in November to discuss what to do.

Balliet said it will take a significant amount of work and money to update the system. However, Balliet said most of the physical work can be done in-house so updates to the Supervisory Control and Data Acquisition System will be the bulk of the project. He said the SCADA system will need some additional instruments installed.

Balliet said he is waiting for a response from DEP, but the individual he needs to speak with has been out of the office. He said once he hears back from DEP, he can update the authority on the status of the project.

Child Advocacy Center of Clearfield County Holds Ribbon-Cutting
Medical Experts Testify at Trial for DuBois Doctor
Tags: ClearfieldClearfield Municipal AuthorityCMAEngineer Jim BallietManager John WilliamsMontgomery DamPennsylvania Department of Environmental Protection

Kimberly Finnigan

Next Post

Child Advocacy Center of Clearfield County Holds Ribbon-Cutting

Please login to join discussion
GantNews.com

© 2020 GantNews

  • About
  • Advertise
  • Newsroom
  • Contact Us

No Result
View All Result
  • Home
  • Top Stories
  • News
    • Top Stories
    • A & E
    • Business News
    • Crime
    • Local News
    • Explore Jefferson
    • Features
    • Health News
      • Health & Wellness
    • Sports
      • Local Sports
  • Obituaries
  • Opinions
  • Classifieds
    • Real Estate
  • Health & Wellness

© 2020 GantNews

Welcome Back!

Login to your account below

Forgotten Password? Sign Up

Create New Account!

Fill the forms bellow to register

All fields are required. Log In

Retrieve your password

Please enter your username or email address to reset your password.

Log In