Week of September 14
CLEARFIELD – PennDOT issues the following travel update for its I-80, Clearfield County project. These restrictions are for the week of September 14. Glenn O. Hawbaker, Inc. of State College is the contractor on this $53 million project. All work is weather dependent.
• Roadwork will take place during daylight hours only but lane restrictions remain in place around the clock.
WESTBOUND:
• There are two westbound work zones.
• The first work zone is located between mile-marker 119 and mile marker 115. The left/travel lane is closed in this area. The contractor will perform concrete pavement patching.
• The second westbound work zone is located between mile-marker 112 and mile marker 106. The left/travel lane is closed in this area. The contractor will be working to remove the 10-foot shoulder.
EASTBOUND:
• The left/passing lane is closed from mile marker 96 to mile-marker 105. The contractor will perform paving work, including the 4-foot shoulder.
• Sub-contractor, Palo, will be working on structure items on the eastbound side.
OVERALL PROJECT
• Motorists can expect delays during work hours. Motorists should also anticipate considerable delays westbound on Friday afternoons & evenings. Motorists can expect considerable delays eastbound on Sunday afternoon and evenings. Drivers should plan accordingly for these delays.
• Speeds are reduced in the work zones to 45 MPH during working hours and
55 MPH during non-working hours. Please be alert for workers on the
roadway.
• Up-to-date travel information should be available to drivers on the Highway Advisory Radio System (HARS) at 1640 on the am dial.
PennDOT reminds motorists to travel with caution through work zones, obey posted speed limits, remain alert for stopped or slowed traffic and always buckle up. For more information on roadway construction and maintenance operations, visit PennDOT’s website at www.dot.state.pa.us.